Hi,
I am exporting Flying logic to MS Project XML format. However when importing into MS Project, all the duration comes up in Hours instead of days. Is there a setting or a way to ensure that this shows up as hours in MS Project?
We are investigating outputting durations of one day or more in days instead of hours, but we need to investigate how a “day” for a task is defined when different resources have different lengths of work days. The change will not likely appear until the next major update.